VISION:  To be the preferred provider of energy and energy services that add value to our member communities.  (Click to discover more about our organization.)

P.O. Box 88920

3724 West Avera Drive

Sioux Falls, SD 56109-8920

 

Tel:  605-338-4042

Fax: 605-334-9753

E-mail:

mrenergy@mrenergy.com

 

 

Pictures Courtesy of DOE/NREL

 

 

This site is best viewed using MS Explorer V4.0 or greater

 

View Photos -  1-20  21-40  41-55  56-65

Photo Gallery Last Updated On   November 21, 2003

 

This page of the photo gallery contains pictures of the second phase of construction at our Worthington, MN wind farm. This most recent expansion project will add two additional wind turbines.

 

The RiverWinds Worthington project is located 2 miles west of Worthington, MN . The first phase of the project was officially completed on July 12, 2002 and four wind turbines are currently producing green power for our numerous subscribers.

Click here for additional details about the expansion project.

It has been our pleasure to use this photo gallery to present to you a brief insight into the construction of a wind farm.

( All Photos in this Photo Gallery are the property of Missouri River Energy Services)

Wind Farm Plat Map

(Click to Enlarge)

56. 10/21/03 - Excavation for the placement of foundation forms for turbines #5 & #6

57. 10/21/03 - Sites #5 and #6 are being constructed just south of turbines #2 & #3

58. 10/21/03 - Large tubular forms are used to form the foundation.

59. 10/21/03 - Installing the forms

60. 10/21/03 - First (outside) form is in place

61. 10/21/03 - Forms installed.

62. 11/21/03 - Construction of units 5 & 6 begins

The first section of unit 6 is positioned. The erection of the first section of unit 5 can be seen in the background.

63. 11/21/03 - Unit 6

Second section of tower is lifted into place.

64. 11/21/03 - Unit 6 with 3rd section in place.

Rotor blades being lifted into position on Unit 6. Construction continues on unit 5 in the background.

65. 11/21/03 - Rotor Blade Assembly on Unit 6

The rotor assembly is hoisted into position. With good weather and skill of the construction crew, raising and mounting of the rotor blades can be completed in approximately 15 minutes.

 

Home Up About RiverWinds Watch us Grow WindKit News Links Feedback Member Websites

RiverWinds.biz may contain links to sites on the Internet that are owned and operated by third parties.
 RiverWinds and Missouri River Energy Services are not responsible for the content of any such third-party site.


Copyright © 2002 RiverWinds

Missouri River Energy Services, the Missouri River Energy Services logo, MRES, MRENERGY.COM, RiverWinds, and the RiverWinds logo are registered and unregistered service marks of Missouri River Energy Services. Power Bowl and the Power Bowl logo are service marks of Missouri River Energy Services and Moorhead Public Service. All rights are reserved in these service marks, and they may not be used without the prior written permission of the service mark owner(s).


Last modified: 12/06/04